Major repairs are being done to the floors in the back rooms of Bunny Camp. The rooms had suffered water damage last year (and probably other years as well!), so a decision was made to replace the floors in both rooms. Grateful thanks to Bob Wheeler, John Cole, Larry Thompson and Stacy Bodder for all their hard work on this and other projects.
First, the bunks were disassembled and stacked away, then the old floor tiles were ripped out and thrown in the dumpster. Once the tiles were out, it was obvious that the plywood underneath would have to come out as well. Once all the flooring was out, we were able to see the reason for the cold temps in those back rooms! The duct work was all flexible tube and was broken and eaten away in many places. While the floor was opened up, new rigid ducts were put in and insulated, additional returns were added some extra electrical outlets were installed.